1. 45 MLD WTP (SCADA Based) for Khandwa Municipal Corporation Khandwa Municipal Corporation PPP (EPC + 23 Years O&M)
1. Design, Build and commissioning of 45MLD WTP
2. O&M for 23 Year
Plant commissioned in May’ 2013 and 2 year O&M is completed out of 23 Years.
2. 42 MLD WTP (SCADA Based) for GVMC Greater Vizag Municipal Corporation, Vizag EPC
1. Design, Build and commissioning of 42MLD WTP
2. Online Water quality measurement using HACK system
Plant commissioned in FYI 2012-13
3. 20 MLD WTP for Dumka Water Supply DWS&D, Dumka, Jharkhand EPC + 2 Years O&M
1. Design, Build and commissioning of 20MLD WTP
2. 2 Years O&M
Plant commissioned in Feb’ 2012 and completed 3 yrs O&M from 2012-2013
4. 45 MLD WTP for Gwalior Municipal Corporation Gwalior Municipal Corporation EPC + 2 Years O&M
1. Design, Build and commissioning of 45MLD WTP with Tube Settlers
2. 2 Years O&M
Plant commissioned in FYI 12-13 and completed 2 yrs O&M from 2012-2013
5. 13 MLD WTP for Nuzvid Water Supply Public Health Division, Narasaraopet. EPC + 2 Years O&M
1. Design, Build and commissioning of 13MLD
Plant commissioned in Feb’ 2015
6. Jangaon Water Supply PHED, Warangal, Telangana EPC + 2 Years O&M
1. Design, Build and commissioning of 11.13MLD
Plant commissioned in Apr’ 2011